India · Nuclear energy
Promises made. Promises missed.
For seventy years, India has announced ambitious nuclear capacity targets. The reactors have rarely arrived on schedule. Here is every target since 1954, plotted against what was actually built.
The promise vs. the build
The black line is what India actually built — total nuclear capacity each year. The dotted line continues it through reactors currently under construction, assuming on-time delivery. Each coloured dot is a capacity target that someone announced. The further the dot is above the black line, the wider the miss.
— · Scroll or pinch the chart to zoom. Drag to pan. Hover any dot for a quick preview; click a coloured dot to pin its announcement, or click a small black dot on the line to see which reactor commissioned that year.
How to read a target
Marker size shows how formal the announcement was: large dots are Plan, Act or Budget commitments; smaller dots are speeches and aspirational visions. The thin red line connecting each target back to its announcement year is its promise vector — it shows when the target was made and how high above the actual baseline it sat at that moment.
Reactor by reactor
Each bar shows a single reactor's evolution: cream where it was a planned proposal, grey while under construction, black once operational, red after shutdown. The lighter grey segments at the right are projected — construction-start plus 8 years, the indigenous PHWR median build time. The red ring, where present, marks the year the reactor was originally promised — only four reactors carry a primary-source-cited original deadline.
Sources & references
Every datapoint plotted above is traceable to one of the following primary or named secondary works.
Reactor commissioning & build status
- IAEA Power Reactor Information System (PRIS), India country statistics. pris.iaea.org
- Nuclear Power Corporation of India Ltd. (NPCIL), site pages for RAPS, MAPS/PFBR, Narora, Kaiga. npcil.nic.in
- Comptroller and Auditor General of India, Performance Audit on Kudankulam Nuclear Power Project, Units I & II, Report No. 38 of 2017. PDF
- World Nuclear Association, India country profile. world-nuclear.org
- Press Information Bureau releases on KAPS-4 full power (PRID 2047270) and RAPP-7 grid-connection (PRID 2111887).
Bhabha-era target announcements (1948–1966)
- M.V. Ramana, "Nuclear Power in India: Failed Past, Dubious Future," Nonproliferation Policy Education Center, 2006. npolicy.org
- M.V. Ramana, The Power of Promise: Examining Nuclear Energy in India (Penguin, 2012).
- Ashley J. Tellis, "Reclaiming the Promise of Nuclear Power in India," Carnegie Endowment for International Peace, October 2024. carnegieendowment.org
Five-Year Plans & the Integrated Energy Policy
- Planning Commission of India, Five-Year Plan documents (1st–12th). NITI legacy archive
- Planning Commission, Twelfth Five Year Plan, Volume 1. PDF
- Planning Commission, Integrated Energy Policy: Report of the Expert Committee (Kirit Parikh, Chair), August 2006. PDF
Indo-US deal era projections
- Anil Kakodkar, AEC Chairman, 412 GW by 2050 projection (2008) — citations via Ramana 2006/2012 and Carnegie 2024.
- Manmohan Singh, address at the International Conference on Peaceful Uses of Atomic Energy, New Delhi, 2009 (470 GW by 2050).
Parliamentary & ministerial statements
- Department of Atomic Energy, Parliament Questions archive. dae.gov.in
- Lok Sabha Unstarred Question No. 4226, answered 21 March 2018 (Jitendra Singh) — 13,480 MW by 2024; 22,480 MW by 2031.
- Lok Sabha Unstarred Question No. 1179, answered 14 December 2022 (Jitendra Singh) — reaffirmation of 22.48 GW.
- Press Information Bureau release, 25 June 2024 — DAE revised target of 13.08 GWe by 2029.
- Parliament question, December 2025 (Jitendra Singh) — current capacity 8,780 MW; 17 reactors under implementation.
Executive announcements & Union Budgets
- Prime Minister's Independence Day Address, 15 August 2024. pmindia.gov.in · WNN coverage
- Government of India, Union Budget 2024-25. indiabudget.gov.in
- Government of India, Union Budget 2025-26 — Nuclear Energy Mission, ₹20,000 cr R&D, 100 GW by 2047. indiabudget.gov.in · PIB PRID 2099244
Central Electricity Authority roadmap
- Central Electricity Authority, Roadmap for Achieving 100 GW of Nuclear Capacity by 2047, October 2025. PDF
Statutory background
- Atomic Energy Act, 1962. PDF
- Civil Liability for Nuclear Damage Act, 2010. PDF
- Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India (SHANTI) Bill, 2025. PRS Bill Track